June 2021 Newsletter

Mon, 21 June

The June 2021 Newsletter is now available.

Read full article

Piling works commence

Thu, 17 June

Piling works for the main structure of the Golden Grove Park ‘n’ Ride carpark have now commenced on site following completion of bulk earthworks.

Read full article

Temporary car park open – 27 April 2021!

Thu, 17 June

The new temporary car park is now available for Golden Grove Park ‘n’ Ride commuters, located next to the SA Districts Netball Association and accessed via Atlantis Drive, Golden Grove.

Read full article

Reusing vegetation

Tue, 08 June

The Ovingham Level Crossing Removal Project is reusing vegetation.

Read full article

Paradise Park 'n' Ride - Community Wildlife Project

Tue, 25 August

Paradise Park 'n' Ride - Community Wildlife Project

Read full article

Paradise Park 'n' Ride - facility opened to commuters

Wed, 05 August

PARADISE PARK ‘N’ RIDE PROJECT

Read full article

Meyer Road Bridge is now complete

Fri, 31 July

Works on the Meyer Road Bridge Replacement Project are now complete.

Read full article

PARADISE PARK ‘N’ RIDE PROJECT - Car park progress update

Wed, 22 July

The Paradise Park n’ Ride project has achieved 71,000 construction hours since mobilisation to site early this year.

Read full article

PARADISE PARK ‘N’ RIDE PROJECT

Mon, 22 June

Stairwell canopy structural steel framing on the new car park deck is complete, with roofing and cladding to commence in the coming weeks. (first image)

Read full article