PARADISE PARK ‘N’ RIDE PROJECT

Mon, 22 June, 2020

Stairwell canopy structural steel framing on the new car park deck is complete, with roofing and cladding to commence in the coming weeks. (first image)

The new path between the bus entry and exit to the Paradise Interchange from Gameau Road is now open. Landscaping is progressing well and will continue over the coming weeks. (second image)

Project update as of 16 June:

• 57,000 onsite labour hours have been worked

• 1,700 cubic metres of concrete placed

• 150 tonnes of steel reinforcement fixed

• 23 tonnes of post tensioning steel cable installed

• 6,500 tonnes of quarry materials imported to site

• 1,000 tonnes of asphalt laid

• 10,000 tonnes of material removed from site

• 1,150 metres of kerb installed.