Early works (late 2020 – June 2021)

Progress of project design

- Currently 70% design

Investigation works

- Underground service locating

Coordination with utility services

- SA Water, SA Power Networks (SAPN), Telstra, NBN, APA Gas

Site clearance

- Removal of earth material

- Building demolition

- Vegetation removal and palm tree relocation

Temporary site fencing installation

- Site compound set-up

- Around construction areas

Pedestrian and cyclist impacts (until end of Project)

- Torrens Road (northern side) footpath, between Exeter Terrace and Napier Street closed

- Exeter Terrace footpath, between Torrens Road and McEwin Street closed

- Torrens Road (northern side) footpath, between Devonport Terrace and Churchill Road closed

- Pedestrian rail crossing directly adjacent Torrens Road (northern side) closed for Gawler Rail Electrification Project (GREP) works

- Pedestrian road crossing on Torrens Road, near Devonport Terrace closed

SA Water main relocations:

- Devonport Terrace and Exeter Terrace

- Torrens Road, between Chief Street and Gilbert Street

Site compounds 

- Set-up offices and access gates for construction areas

Early piling works for offline bridge construction

- Preparation works

- Construction of piling pads

- Pilling rig mobilisation

- Continuous Flight Auger Piling commences

Minor civil roadworks

- Preparation works for Traffic Switch 1

- Removal of road median along Torrens Road and Churchill Road

- Realignment of existing road lanes

- Installation of temporary traffic signals to prepare for Traffic Switch 1

Bus stop changes

- Permanent closure of Bus Stop 8 Torrens Road North

SAPN stobie pole removals 

- Torren Road, between Hayman Street and Wattle Street

- Exeter Terrace, south of McEwin Street

Ongoing traffic management- lane and speed restrictions, side road closures and detours.

Stage 1 - Offline construction of the bridge (third quarter 2021 – first quarter 2022)

SA Water main relocations:

- Torrens Road, between Wattle Street and Drayton Street

- Torrens Road, between Chief Street and Gilbert Street

- Churchill Road, between Torrens Road and Avenue Road

Traffic Switch 1

- Remove right turn movement from Churchill Road onto Torrens Road

- Remove left turn movement from Torrens Road onto Churchill Road

Commence offline bridge works

- Construction of bridge columns

- Construction of approach ramps

- Installation of bridge beams

- Installation of bridge deck

Civil roadworks

- Including pavements, kerbing, road median and temporary line marking

Rail works

- Modify overhead gantry and wiring works

- Construction of gantry in a new location, to enable bridge construction

- Removal of redundant gantry

Churchill Road roadworks - western side

- Widening and elevation of the intersection

- Construction of new pavement

Pedestrian passive and activated road crossings

- Churchill Road, south of Avenue Road passive road crossing opened (prior to Traffic Switch 1)

- Torrens Road and Churchill Road, near Guthrie Street activated road crossing closed

- Churchill Road, south of Guthrie Street activated road crossing opened

Pedestrian rail crossings 

- Southern pedestrian access to Ovingham Railway Station remains closed once GREP works are complete, to enable bridge works

- New northern rail crossing remains open

Bus changes

- Bus Stop 8 Churchill Road (west side) to be shifted further north, near Avenue Road b

- Bus Stop 8 Torrens Road (south-west side) to be shifted to outside 35 Torrens Road

The Project will work closely with GREP to coordinate and minimise public transport service impacts

Pedestrian and cyclist detours remain in place

Ongoing traffic management- lane and speed restrictions, side road closures and detours and a weekend of major traffic restrictions

Rail service impacts (weekends and night closures), substitute bus services in place (Gawler Rail Electrification Project (GREP))

Stage 2 – Reconfiguration of Torrens Road and Churchill Road intersection (first quarter 2022)

Traffic Switch 2

- Realign traffic along Churchill Road

Churchill Road construction works - eastern side

- Widening and elevation of the intersection

- Construction of new pavement

Completion of offline bridge works, in preparation for Stage 3

- Construction of approach ramp

- Bridge fit out

- Installation of permanent traffic signals and road signage

Civil roadworks

- Pavements, kerbing, road median and temporary line marking

Commence landscaping works

- Detention basins

- Footpath

- Excavate and level out earth material for playground and activated area under bridge

- Irrigation

Staged testing and commissioning

- SAPN bridge lighting

- Traffic signals

Bus changes

- Stop 8 Churchill Road (west side) install in final position

- Stop 8 Churchill Road (east side) relocate further north

Pedestrian and cyclist detours remain in place

Ongoing traffic management- lane and speed restrictions, side road closures and detours and a weekend of major traffic restrictions

Rail service impacts (weekends and night closures), substitute bus services in place (GREP)

Stage 3 – Partial opening of bridge to traffic (Second quarter - June 2022)

Traffic Switch 3

- Realign traffic onto new bridge

Complete bridge ramp construction 

- Completion of approach ramp

- Bridge fit-out

- Installation of permanent traffic signals and road signage

Finish off road signage 

- Static signage

Surface roads construction

- Torrens Road, between Guthrie Street and Chief Street (both sides of Torrens Road)

Civil roadworks

- Along Torrens Road, between Park Terrace and Wattle Street

- Pavements, kerbing, road median and permanent line marking

Level Crossing removal (Easter long weekend)

- Removal of asphalt on Australian Rail Track Corporation (ARTC) track

- Recondition Adelaide Metropolitan Passenger Rail Network (AMPRN) track

- Update rail signalling

Testing and commissioning

- Local council lighting

- Rail signalling

Continue landscaping works

- Tree, shrub and grass planting

- Mulch and footpaths

Community activation and public artwork

- Completion of playground and activated area under bridge

- Installation of public artwork

Bus changes

- Adelaide Metro routes 230, 232, A016, 951 (school bus) realigned to bridge

- Open Stop 8 Churchill Road (east side)

- Open Stop 8 Churchill Road (west side)

All bus stops in permanent locations

Pedestrian and cyclist detours remain in place

Ongoing traffic management- lane and speed restrictions, side road closures and detours

Rail service impacts (weekends and night closures), substitute bus services in place (GREP)

Stage 4 – Full opening of bridge to traffic (third quarter 2022 – March 2023)

Bridge fully operational

  - Realign traffic onto new ramps and bridge

Complete road median works along bridge

Surface roads construction

- Torrens Road, between Guthrie Street and Chief Street (both sides of Torrens Road)

Civil roadworks complete

Landscaping works complete

Community activation and public artwork complete

Demobilisation of site compounds

PROJECT COMPLETION

Ongoing traffic management- lane and speed restrictions, side road closures and detours.