Trains running through the new Oaklands Railway Station

Mon, 06 May

Thank you to the project team who worked 24/7 for three-weeks to connect the new station and rail corridor!

Read full article

Occupation progress

Tue, 23 April

The occupation works are well underway! The Seaford and Tonsley lines are temporarily closed until last service Sunday, 5 May, while the project works 24/7 to connect the new station and rail corridor.

Read full article

(Rail) track progress

Tue, 02 April

Ballast, sleepers and rails are officially in!

Read full article

Upgrade and closure of pedestrian/cyclist rail crossings

Mon, 01 April

As part of the State Government’s Railway Crossing Safety Improvement Program, crossings throughout Adelaide have been identified for review, upgrade or closure based on factors including safety risk profiles, pedestrian and cyclist counts, crossing history and technical data.

Read full article

Connecting the new station and rail line - Temporary line closure April and May 2019

Sun, 17 March

To connect the new station and rail line, the project needs to temporarily close the Seaford Line for three weeks in April and May 2019.

Read full article

Roll in the rail infrastructure

Thu, 14 March

Rail track infrastructure is now at the site compound, and the project has started welding in preparation for installation.

Read full article

Installation of the pump station

Fri, 08 March

With the construction of the rail underpass, a new drainage system was required to discharge rainfall to the local stormwater network. Throughout February and March, the project has been building a pump station to remove future rainfall in the new lowered rail line.

Read full article

Staged car park construction

Fri, 22 February

The project has completed stage one of the commuter carpark upgrades, with stage two to commence soon.

Read full article

Dunrobin and Diagonal Roads intersection works

Fri, 08 February

Works to upgrade the intersection of Dunrobin and Diagonal Roads are well underway.

Read full article

Working through the night

Thu, 07 February

The project is working night shifts to tackle key tasks in the lead up to connecting in the new station and rail line, planned for April 2019.

Read full article