Skip to main content

First car park deck concrete pour

Thu, 16 April, 2020

Works on the Paradise Park ‘n’ Ride project are coming along nicely, with formwork and reinforced steel recently installed on the car park deck in anticipation for the first major concrete pour, which was successfully undertaken this Wednesday, 8 April.

A total of 270m3 of concrete was poured to form the concrete deck. A further three large concrete pours will occur over the next 4 weeks.

In addition, the retaining wall of the new ground level car park is now almost complete, following the installation of 39 steel piles and pre-cast concrete panels.

For more information on the project or to sign up for project updates, visit https://ptpa.com.au/projects/o-bahn-park-n-rides