Dunrobin and Diagonal Roads intersection works

Fri, 08 February, 2019

The intersection will be upgraded to a signalised intersection, to help with traffic flow in the local area.

The project has been working on night shift since December 2018, to install underground traffic signals and road lighting conduits in the two busy roads. Next the project will focus on stormwater, kerb demolition, pavement widening and asphalting works.

The existing pedestrian crossing on Diagonal Road, just north of Dunrobin Road, will be shifted further south, to line up with the new signals.

The project will continue night shift to undertake these works over the coming weeks, with some days works. During works, there will continue to be lane and speed restrictions in place, with any traffic intrusive works to take place outside of peak hours.

The new signalised intersection is expected to be complete in April 2019.